Update on Village Park

Representatives of the Alliance and the CHB Progress Association met with Rose Group on 4 December.

Community liaison meetings are required under the Beaches project approval conditions; it is the intention these meetings are to occur monthly for the duration of the works which have an expected completion date of June 2024.

The project scope includes

o   Village Park

o   Reconstruction of Hale Street

o   Headland reserve

o   40 lot residential subdivision

 

Project status 

o   Works commenced 3-4 weeks ago under supervision of Auditors and Geotech specialists

o   Current focus bulk earth works and land clearing

o   Removal of trees now complete

o   Berms and sediment controls to control runoff being constructed

Approval and Certification process

o   Landscape and stormwater design not yet approved by Lake Macquarie Council (LMCC); approval expected soon

o   Final plans will be shared with community once approved

o   Once works completed will hand over to LMCC; 5-year maintenance obligation on village park and 1 year on streets.

 

Design Details                    Village Park

o   Majority of village park will be subject to fill

o   Riparian zone below the pond

o   Gross pollution trap in pond on high side, wire rope around pond (similar to existing ponds in Beaches)

o   Park playground “natural play” low key construction timber blending into landscape with benches, bike racks

o    No picnic tables or BBQs

o   Village green footpaths will be concrete southern end, others crushed stone

Hale Street

o   Hale Street being moved slightly east of current location

o   Street will be 9 metres wide, parking on western side only; no cycle way; no speed humps however will have a curved design

o   Intersection of Hale and Flowers/Lindsley to be constructed April/May 2024

o   Street lighting approved; pole type same as beaches

Question on notice: Does the design of village park achieves the visual separation required as condition of consent?

Next meeting proposed February 2024.

Thanks to Damien Hawcroft for organising this meeting.

Previous
Previous

Community Forum with Rose Group on Shop Plans

Next
Next

RFS bushfire briefing session 21 October 2023